PS - PPM (Item) Integration of actual hours

$
0
0

Hi all,

 

I have setup automatic accounting integration, but I'm facing issues when I want to transfer actual hours from PS to Item capacity Planning. I post hours via CAT2 and run CAT7 report afterwards in ERP. I can see the hours in the project i  ERP. I run /RPM/FICO_INT_PLANNING in PPM (with Integration and Planning selected) and I can see the cost of the hours in RPM_FIDATA. I posted some hours in February and some hours in March.

 

My issue is, that I can only see the hours posted in February in my Item Capacity Planning. I can't see the hours posted in March. Posted with same sender cost center, same CO area, same act. type, same wbs element.

 

I tried to run /RPM/CAP_PLAN_INT report as well. When I run this the hours does actually show for both February and March, but the hours doubles.

 

 

Anyone who can help me?

 

br,

Morten