hell
Trying to account ECV.
The formula is
ECV = [(NPV pcs - C) pts - D]
Where:
pcs is the probability of commercial success.
pts is the probability of technical success.
C are the launch costs.
D are the development costs.
in my case NPV is -20.602.881,63, pcs - can't see it in project, pts 058, and i can't find there is Launch costs and Development costs - Could anyone share path and/or screenshot?