Hi All,
I am facing a Problem regarding CATS/PPM integration.
We are filling time sheet against internal order and rolling this data to cProjects, which is working fine i.e actual hrs. reflecting correct at my task level in confirmation section after filling time sheet and running report DPR_CPR_CATS_TRANSFER report.
After that to roll up actual resource cost/time we are running report /RPM/FIN_PLAN_INT and RPM/FICO_INT_PLANNING and we can see actual resource cost coming correctly at item financial planning but to get actual resource hours at item capacity planning screen when we are running report /RPM/CAP_PLAN_INT , nothing happens i.e.actual resource hours(filled time sheet values) are not getting updated, however other heads like assigned resource(from cProjects assignment ) are comming correct.
Appreciate if someone can help how we can get actual resource hours after filling time sheet.
Thanks
Amit