Hi Experts!,
I am working with PPM 5.0, and I am searching a solution to resources management. I can create the resources through the browser, but I realized I have to create a link to the resource in the PPOME transaction to see these resources when I want to assign them into the cproject. (If I do not assign the resource in the PPOME, I can not see the resource in the candidate list into the cproject).
So, I would like to know if exists any chance to do a resources segregation, I mean, when I want to assign a resource into a cproject that belongs to specific portfolio, I would like to display only resources of the specific portfolio. Is it possible?
If I mentioned is not possible, exists any possibility to segregate the resources by geographic area or anything?
Thanks in advance.
Regards.