Dear SCN Folks,
I facing an interesting situation in NWBC 4.0 PL 19 (Oil & Gas)
Any time I am trying to set up a successor or a predecessor relationship in the test system, the dependence between the tasks are not prevailing. ( I mean here the start-finish; finish-finish; etc. relationships between the tasks)
We do not have here custom coded versions forced on the system, so this should be a core SAP switched-off situation. I am wondering If I can switch-on this function with SPRO in GUI, but I am searching a needle in the haystack.
If anyone knows about the place where I can configure these with SPRO, please share.
Many thanks in advance,
Adam