Hi All,
I am using PPM 6.1
What is the significance of Task Type in PPM - Project Management ?
I find the following issues
1. Unless I set the task type, I cannot release the task. What could be the reason? Can I eliminate the usage of Task Type field?
2. I have defined custom task types in customizing, however these are not reflected in the Project Template. Instead I see them in User Settings --> Defaults in project template as well as the operational project.
Image may be NSFW.
Clik here to view.
Image may be NSFW.
Clik here to view.
3. Even after setting the defaults, the default values for task type are not getting set when I create a new task or a new operational project from the template.
Image may be NSFW.
Clik here to view.
Please provide guidance on usage of this field. Also why I am not seeing my custom task types in the operational project tasks?
Regds,
Ashwini