Hi All,
I am using PPM 6.1
What is the significance of Task Type in PPM - Project Management ?
I find the following issues
1. Unless I set the task type, I cannot release the task. What could be the reason? Can I eliminate the usage of Task Type field?
2. I have defined custom task types in customizing, however these are not reflected in the Project Template. Instead I see them in User Settings --> Defaults in project template as well as the operational project.
3. Even after setting the defaults, the default values for task type are not getting set when I create a new task or a new operational project from the template.
Please provide guidance on usage of this field. Also why I am not seeing my custom task types in the operational project tasks?
Regds,