Hi All
Case of requirement:
Task1 lasts for 0.5 days and the subsequent task2 takes another 0.5 days. So the whole time frame of task1 and task2 is 1 day in total. But in the standard system the minimum time of each task's duration is 1 day. In this case task1 and task2 will take 2 days instead. And this will make the schedule of the project longer than the fact is.
Whether the duration of project elements can be set to decimal format or change the time unit from day to hour?
Regards
Jimmy