Hello,
I have linked an Item with a PS project (account Assignmt) and executed transfer from ECC to PPM. All is OK on the planning view of the Item, i can see Actual costs on the actual view i have customised.
I then took off the link with the project et excuted again RPM_FICO_DATA_TRANSFER. Table RPM_FIDATA is emty for that Item but when i go to the planning screen of the Item, I still see actual costs.
I have tried /RPM/FIN_PLAN_INT but without success.
Thank you for your help.