Interchecklist relationship

$
0
0

Hi All,

 

When we are trying to create project from an existing project using Copy Project relationship between Interchecklist Tasks get broken.

 

e.g. Let's say we have Project A and it has Phase A . Now under this Phase A we have checklist A & B. In Checklist A We have Checklist Item ABC which has Task 1 , Task 2. In Checklist B we have checklist Item XYZ which has Task 3, Task 4.  Now Task 3 has predecessor Task 1 and Successor Task 4.

 

Now when I copy Project A to Project B using Copy Project Relationship between Task 3 and Task 1 get's broken as they belong to different Checklist. Whereas relationship between Task 3 and Task 4 remains as it is. In addition to this if we move any project element up or down relationship of that element also get's vanished.

 

We would like to keep this relationship, we came across the BADI "DPR_COPY_FINALIZER" but it doesn't suffice this.

 

 

Regards,