SAP Noted 1840729: Implemented, program: ZSCHEDULE_FICOINT_PLAN_ADVANCE

$
0
0

Dear Experts,

 

SAP has given us program ZSCHEDULE_FICOINT_PLAN_ADVANCE (as per Note 1840729) and this program contains almost all parameters of program /RPM/FICO_INT_PLANNING.

 

I am facing some issues while creating variants to schedule a background job to run this program.

PPM.PNG

 

Actually, 1) I am not sure what this field' Number of free work processes' is all about? Which value should I enter here to make my variant more meaningful and efficient in running.

2) Item count(job size): What should I keep in this field vacant and run my variant. Is this field has any co-relation with field 'Number of free work processes'?

 

We are using 3 portfolio's and I have created 3 variants, 1 for each portfolio. Each portfolio contains some 1000 items inside it.

 

So, kindly help me in setting up these variants for a smooth and efficient job run for this program.

 

Best Regards

Saurabh