I have all the integration configuration in place between CATS and PPM which are on separate instances. Projects in PPM and PS are Released.
The PS project is not configured for Automatic creation from PPM. It is created Manually and then Object Links to Item+Project and Account Assignment is done later. The FI data is flowing correctly to PPM. But the CATS worklist is not getting filled, neither are the hours posted in CAT2 after the report DPR_CATS_CPR_TRANSF triggering an IDOC to PPM.
Does it matter for CATS Integration to work to have the PS project created automatically from PPM?