Quantcast
Channel: SCN : Unanswered Discussions - SAP Portfolio and Project Management (SAP RPM, cProjects) and cFolders
Viewing all articles
Browse latest Browse all 661

Importing Microsoft Project to cProjects

$
0
0

Dear Experts

When importing MSP to cProjects, we want to update some information of tasks, such as task description but to keep other information like the assignment of role and resource by the same time.

Howerer, when I update current project with sturcture only, I get the following message. The system deleted and regenerated the tasks. So other information of tasks are missing after importing. I'm wondering does this have anyting to do with the mapping fields between MSP and cProjects.

Thanks for any clue. We are using PPM5.0.

       

 

Regards

Ymei


Viewing all articles
Browse latest Browse all 661

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>