Project structure status and Item status synchronization issue
Hello All, we are facing the issue with the status synchronization for Project structure status and Item status. in our case we have two scenario. 1. change of status of project structure...
View ArticleVersions
Hi, I need to understand the relationship between the number the system assign to a PPM Item when creating a version. I noticed on data source 0RPM_PORT_ITEM_MANAGEMENT that a 12xxxxxxx EXTERNAL_ID is...
View ArticleCannot convert key figure value to metrics unit or currency
Hello experts, we have some metrics in the fin info tab. while moving to this tab there is some error coming. Cannot convert key figure value to metrics unit or currency. have already checked the...
View ArticleHow to control a field on cProject through any tool like "screen and...
Hello Experts,Could you please suggest me if there is a way in PPM to control cProjects field through a way other than standard field control settings?May be some way of "screen and transaction...
View ArticleUser Defined WBS Element name as per existing PS coding mask while creating...
Dear Experts, I have below concerns after automatic creation of WBS elements from cProject in thread Creation of PS WBS Element for selected cProject element 1. Would it be possible to create WBS...
View ArticleAuthorization control to display portfolio items .
Dear Experts, I have got one requirement regarding authorization to access Portfolio objects. it is like this, In our scenario we have buckets created for continents then for country and then created...
View ArticleNot able to create Project from portfolio item screen and Not able to edit...
Hi Gurus, Normally we can able to create project from the portfolio item screen (after creating portfolio item) using an option "project". Project will be created with same number as same as portfolio...
View ArticleCustom field at Phase and Task level
Dear All, I have a requirement where I have to add a custom field in the below components - same custom field in both these viewsView VI_DET_ADD_PPO of WD component DPR_DET_DATA_PHASE_O andView...
View ArticleFin planning default view expanded
Hello Experts, Is there any possibility to set the Default view in the fin planning with selected fin Groups or views expanded ? Best regardsLS
View ArticleFin planning months instead of periods
Hello Experts, is it possible to Display the months in the fin planning instead of the periods. currently it is showing as 01, 02 , 03 and not Jan, Feb , Mar. Please advise. Br,LS
View ArticleProgrammatically Change Initiative Status
Reviewed programs RPM_DX_INIATIVE and INM_INITIATIVE_TEST but neither appears to be able to update STATUS. Have tried multiple attempts at debugging the actual dynpro logic but am getting no where...
View ArticleItem creation when initiative was created
Hi experts, I have an issue, I need to created an Item when the user created an initiative. I try to create the item using the methods end of transactions of these badis:...
View ArticleCreation of PS Network/Activity for selected cProject element
Dear Experts, Thanks for helping in creating the WBS element automatically from cProject structure using account integration. Will it possible to create network and activity in Project System from...
View ArticleMetrics are not appearing under Deliverable tab of Portfolio Item
Dear Experts, Could you please help me why the metrics are not appearing under Deliverable Tab ? I have defined the Metrics under Common Function for object RIH and also mapped it to Item Type. Did I...
View ArticleNPV, IRR, ROI and Payback Periods Calculation in portfolio item
Dear Experts, I am using PPM 6.0. I have gone through the thread : NPV and IRR Calculation in portfolio item which is marked as correctly answered. Could you please tell me the detail config for this...
View ArticleSSL_ERROR_RX_RECORD_TOO_LONG when trying to open 1 PPM Project
Dear PPM Guru, I am trying to get my CPRXRPM 610_740 - SP 0 (PPM 6.1) on my IDES EHP7 working.I did follow this thread https://scn.sap.com/thread/3779302and apply most of (ConfigContPPM61SP01.pdf). and...
View ArticlePPM Resource Search - Hide Column Location
Dear All, I have activated the integration of HR to create automatically BPs (not the ALE interface). The problem is that I can't define which infotypes to be transferred. So I need some help in order...
View ArticleUnable to Transfer to ERP due to error "No Planning Element has assigned to...
Dear Experts, I am unable to transfer the cost to ERP due to below error "No Planning Element assigned to this item". I confirm the Financial View and the Portfolio Type configurations are correct. I...
View ArticleSynchro dates from project phases to item decision points
Hi! I am trying to configure dates synchronization between project phases and item decision points.earliest start date of phase should be copied to planned start date of related decision pointearliest...
View ArticleScheduling in Cprojects
Does any one know how to enable CProjects so you can choose to schedule either top down or bottom up perhaps where there is a pop up selection that allows you to change scheduling method (top down /...
View Article