Hi Team,
In my scenario, we are creating the Portfolio Item which in-turn creates C-Project automatically. Then we link the Project Phase to WBS Element of R/3 using OBJECT LINK (as this WBS will hold the Planning & Actual cost from logistic modules).
Please not we are not doing any planning in C-Project although we have activated the FI integration and done the necessary configuration in Project Management.
I have two question over here :-
1. How can I bring Plan and Actual cost of PS WBS back to C-Project Phase?
2. When I'm running evaluation (Costs and Revenues of Linked Objects) it dose not roll up the values to the Phase and PD of c-project. Is I'm missing something?
Appreciate your help.
Thanks
Gaurav