Quantcast
Channel: SCN : Unanswered Discussions - SAP Portfolio and Project Management (SAP RPM, cProjects) and cFolders
Viewing all 661 articles
Browse latest View live

Metrics Management

$
0
0

Hi,

    There is this table INM_M_OBJ_MET_VA which has the information about the values that we input against each metrics within metrics management. Could someone let us know how to relate the GUID present in the table to the portfolio-item guid?


thanks


Metrics management - key figure calculations

$
0
0

Hi,

        We have a requirement wherein we need to display 3 different metrics within the key figure monitor. Metrics A and B are to be manually input and Metric C is to be calculated based on A and B ( example c = a + b). Is there any BADI that we can make use of to achieve this? Your input is highly appreciated.

 

thanks.

Page can not display in PPM6.0

$
0
0

HI experts,

 

our basis had installed the IDES EHP7 including PPM6.0, and I have done some configurations.

 

now the problem is that, if I click to create a project or a portfolio, the webpage will not be displayed.

 

I have checked that the URL address will be redirected to an unknown address. for example, my correct URL should be http://test.corp.com:8000, but after I click to create a new project, the URL of pop-upped page will be http://eccde.wdf.sap.com:50080.  Strange!

 

am I miss some configuration steps? can anyone help me on this.

 

please also kindly refer to this issue, it is similar as mine:

Page cannot be displayed while Creating Portfolio

 

Thanks

William

Certificate does not exist

$
0
0

Hi,

       We are trying to upload a document from within the "Documents" tab in cProjects. Once the check-in button is clicked, we get an error "Certificate does not exist". We have this problem in the dev system. Could someone throw some light on what the problem could be?

 

thanks much.

 

Regards.

bucket authorization object, how to manage it with PFCG

$
0
0

Hi To all,

I'm quite new in the PPM world and I'm currently facing an issue with authorization objects. I created a custom user Role, starting from  SAP_CPR_USER.

I would like to add the bucket object authorization : if I assing this tole to a user, it won't be enabled to select buckets .

 

How can I manage it? I've tried to search on the internet , finding something on RPM , but did'n get the logic, neither I've understood how to set it eventually.


Thanks a lot!

Carlo

Custom field not visible for Project Definition in PPM 6.0

$
0
0

Hi all,


I have done the SPRO configuration required to add a custom field in Project Definition and it worked out. However, I need to add more custom fields and they are not displayed. I’ve done the following procedure:


1. Enhance DB table. added  the field in structure DPR_TS_PROJECT_EXTENDED_ATTR, object type DPO

2. Define field groups for custom fields

3. Set up field control.

4. Restart the SAP server


The custom field tab has come after making SPRO changes. But the field is not visible on the tab.


Please let me know if I am missing any steps.


Thanks,

Anna

Bucket Rollup

$
0
0

Hi all,

 

Anyone who knows if it is possible to enhance the /RPM/BUCKET_ROLLUP report so that it is possible to specify a single or multiple Items that you want to perform this for. Then rolling up from Item to the bucket and from bucket to parent bucket until the bucket has no parent bucket, making sure it is rolled all the way up the hierarchy.

 

Hope you can help,

 

Br,

 

Morten

User Status Maintenance

$
0
0

Hi Experts,

 

We have a "User Stat." field in tasks and projects dashboard, I'm just wondering where in cProjects these user status can be maintained.

Please see screenshot below for your reference.

user status - tasks.JPG

 

Thanks,

James


Save Custom fields to custom DB at FPM_SAVE method for item create or change

$
0
0

Hi Guys,

 

I have created a Custom WDC and added as a main view( new tab) on fpm_oif_component by enhancement component configuration( RPM_ITEM_DETAILS_OIF). How to save these contents to custom DB table when click on SAVE button in toolbar.

 

Please guide me.

 

 

Regards,

Paul.

Item Classfication Factor %

$
0
0

Hi All,

 

Does anyone know if it is possible to have a default value in the factor % when choosing a classification bucket in the Classification hierarchies.

 

As of standard the factor % is blank.

 

Br,

Morten

Workflow - Insertion

$
0
0

Hi Gurus,

 

We are facing a  issue in the workflow for appropriate request. We have 13 levels  of approvals for  an AR. Of the 13 approvers two has resigned and their userid's are deleted from ECC6. At the moment we are manually forwarding the request using TC SWIA.  In all the request we have added  new 2 approvers in the place of resigned approvers using TC IMA2N. Even then we have to forward manually all the request to the next approver. Is there any method to avoid manual forwarding.

P.S , We have added the 2 new approvers in the approver list using TC OITN.  How to replace for all the request at one go replacing the deleted approvers with fresh approvers.

Please help

 

Regards

Vidhyadharan

cProjects : Mass updation of dates for phases and tasks

$
0
0

Hi Experts,

 

Need to extend the project Phase and Tasks, resource assignment to 31-01-2015, for multiple projects which contain more phases and tasks.

Is there any standard program to change the end date of Phases, Task and resource assignments?

 

Thanks in Advance.

Regards,

Venugopal.R

Project VIEWDATA.CALCULATED_FINISH_DATE saving 1 day more in CATSDB

$
0
0

Hi All,

 

I am having a issue with 'calculated finish date' from view 'viewdata' for a project. When we are saving this data from portal it is saving in ECC catsdb table with 1 day more (Ex: if we are saving as 02/24/2014 in portal, it is saving as 02/25/2014 in ECC). When I am trying to read this date into CAT2 tcode I am seeing the date with 1 day more. But when I pull the same project in portal it is showing the correct value that we saved (without adding 1 day more).

 

While reading the data into CAT2 tcode I can subtract '1' and the original data. But i want to know how the data is ulling correctly on portal so I can use the same method while I am trying to read to CAT2 tcode.

 

Any help/documents/link is appreciated.

 

Thanks in advance,

Karuna

 


Confirmed Work Report

$
0
0

Hi Experts,

 

Is there a way we can see the total confirmed work(dates and works tab) for each Project at least in the Projects Dashboard?

 

Sample Dashboard view we want:

 

Project (Number)Project DescriptionPriorityTotal Confirmed Work

 

 

We also want to see the total hours of confirmed work allotted by a resource in the Resource Overview in the Resources tab of the project.

 

Sample Resource Overview we want:

 

ResourcesDistributedStatusRem. AvailabilityAvailabilityAssigned EffortUnitTotal Confirmed Work

 

 

 

 

Thanks,

James

Threshold value violation for phases

$
0
0

Hi,

      We would like to check if a particular phase has not been approved before a certain date and assign a severity for it automatically. We would like to know the status to be entered for "SYSTEM-STATUS"  in the formula for threshold as the status of the phase would be "For Approval - Released".

 

thanks.


Item To Cproject Object Link

$
0
0

Hello Friends,

                   When searching in here we found out the basic object link for costing rollup is 0RPMFIPROJECT. When we manually create object links between item and cproject it is working fine.But, we want to automatically create object link between Item and Cproject when we create item from project using Create Project on Saving.Is our understanding is proper? Or is there any other configuration is to be done for creating the Automatic Object link between item and Cproject ?

 

 

--

Thanks,

Alex

Default document folders from Project template not copied in project

$
0
0

Hi,

 

I have a set of default folders in the document section of a Project template. But when i am creating a project of that template, the document folder list is not getting copied. Where can i debug to find the issue? I can see the list of folders/documents are there in the table DPR_DOCUMENT for the project template but while creating even after saving, i can see only the root folder getting created.

 

The issue is coming after we upgraded our system to PPM5.0. It was working fine earlier.

 

Anyone faced the similar issue?

 

Thanks,

Pavan.

BADI when create Item Portfolio

$
0
0

Hello Guru's:

 

I need to know if exits a BADI at Item Portfolio creation. Because when Item Portfolio create i need to save dates into differente decision points.

 

Best regards,

Mariano

Task and Projects to person responsible maintenance

$
0
0


Hi Experts,

 

Problem:

I can't find the table or view where SAP PPM maintains the relationship between tasks or projects to person responsible. I already browse from different tables(DPR_PROJECT, DPR_TASK,RPM_FES_MANGER_A) and tried to trace it but I can't.

 

 

Objective:

To simplify, I want to build a reports/view that have the following columns:

 

1st:

Project ID

Project Name

Project Category

Project Type

Person Responsible

 

2nd:

Task ID

Task Name

Person Responsible

 

 

I already found CGPL_TEXT where SAP PPM maintains the information I need like the project and task name. I also found RPM_FES_MANGER_A where the names of person responsible is being maintained along with its RESOURCE_GUID. I just need the table that at least shows the ff. fields.

 

PROJECT_GUID

RESOURCE_GUID

 

 

 

Thanks a lot,

James

PPM Item Capacity Planning integration with SAP PS

$
0
0

Hi ,

 

I am using PPM 5.0. PPM item integration with SAP PS project. I am planning to update planned/actual work hour from PS project to PPM item Capacity Planning.

 

I have maintained the proper setting like Cost element mapping to capacitu categoty, capacity group and view. Capacity view is set as integration. PPM item has object link with PS WBS. The Global setting also maintained.

 

When I use the report /RPM/FICO_INT_PLANNING, it does not update the capacity planning view from PS project. But Finance view is updated properly.

 

Is there any extra setting needs to done?

 

Thanks,

Morshed